Required modification of Burner/control system
Load control modification with external signal processing unit, adjustment of post purge timer. Recommission on MGO.
Recommendation for burner
Test flame pick up on MGO and replace non-responding and IR-type flame sensors.
Fuel supply system and change over automation
Install new MGO fuel line with automatic change over. Alternatively the existing line can be modified to operate on MGO, but this is not recommended unless space does allow for a new line.
Required modification of Burner/control system
Adjust oil pressure.
Recommendation for burner
Test flame pick up on MGO and replace non-responding and IR-type flame sensors. for burners used for inert gas generation, a load control modification is required.
Fuel supply system and change over automation
Install new MGO fuel line with automatic change over. Alternatively the existing line can be modified to operate on MGO, but this is not recommended unless space does allow for a new line.